The official details and key dates of the Warriors proposed new Arena in San Francisco are now emerging, as reported by SocketSite.com.
∙ October 2012: Homeowner Association Meetings and Public Outreach
∙ October 16, 2012: Conceptual Drawings, Framework and Fiscal Feasibility Presentation
∙ October 23, 2012: Port Commission Action on Framework and Fiscal Feasibility
∙ November 20, 2012: Board of Supervisors Action on Framework and Fiscal Feasibility
∙ November 21, 2012: Notice of Preparation for EIR issued by Planning Department
∙ December 2012 thru 2013: Bay Conservation and Development Commission (BCDC)
Design Review Board (DRB) Hearings
∙ January/February 2013: Port Commission Hearing and Action on Term Sheet
∙ January/February 2013: Board of Supervisors Action on Term Sheet
∙ Summer 2013: Planning Commission Hearings: Environmental Impact Report (EIR)
∙ Late Fall 2013: Certification of EIR; adoption of Zoning and General Plan
Amendments and approval of Conditional Use permits if required
∙ January – April 2014: Board of Supervisors Action on Transaction Document
∙ January – April 2014: BCDC DRB Action on Project Design
∙ January – April 2014: BCDC Major Permit & Public Trust Consistency
∙ January – April 2014: Other regulatory approvals
∙ Summer 2014: Proposed Start Construction
∙ Summer 2017: Proposed Complete Construction
You can read the full article, HERE.